Enter Constraint log from menu
Step 1

- Click on the Constraint log icon
 
Step 2

- Click on Add constraint
 
Step 3

- Enter Constraint, Activity constrained, Person responsible
 - Select the date To be resolved
 - Click Done
 
Step 4

- The constraint log will then be updated
 
Add constraint log through a tag
Step 1

- Double-clicking the tag
 
Step 2

- Click on Add constraint
 
Step 3

- Enter Constraint, Activity constrained, Person responsible
 - Select the date To be resolved
 - Click Done
 
Step 4

- The constraint log will then be updated
 
Review constraints
While reviewing the constraint log, you can select from open, closed, and all constraints

- Show Open Constraints
 

- Show Closed Constraints
 

- Show All Constraints