Milestones are not automatically adjusted, as this typically requires a discussion to determine possible actions to mitigate. The tag not completed or moved late will have a visual indicator on the successor tag to indicate there is an issue to be addressed. Additional days can be added to an activity to compensate, or the successor activity can be moved.