March 2025 Release

New

  • In the phase pull area:
    • You can now add Master activities directly into the phase pull lanes in addition to the Master activity lane.
    • A master activity can be deleted
    • If a master activity has a trade that is exactly the trade name in the plan, it will populate that tag with the trade name and colour in the phase pull lanes when it is moved there.
    • When an activity is dragged from the Master lane it will remain the size it is and will snap to the dates that it is scheduled.
    • When an activity is dragged from the Master lane to the phase pull lanes, the edit dialog opens
  • 10 additional colour choices have been added to the reasons for variance dialog
  • In the activity report, nonworking days are now displayed, and the activities are shown if they are on these days.
  • When activity tags are moved past the end of a lane, the lane auto expands to accommodate them.

Fixes

  • Repair the view of the PPC report in varying window sizes
  • On the PPC report, the % number colour indication has been corrected.
  • In the phase pull, the lane sizing control now remains in view when the plan is zoomed.
  • When a lane has ended the space that it occupied is collapsed.
  • Make Master milestones visible when they overlap.
  • Repair phase pull lane resizing behaviour.
  • Improve the visibility of the phase pull lane size control
  • Multiple fixes of milestone behaviour in the phase pull area.

Tip: If you wish to pin Visual Planner to the taskbar, you need to use the right click menu either in your applications list or on your desktop. Do not use the menu from the taskbar or Visual Planner will not automatically update

 

 

 

 

 

Was this article helpful?

Updated: March 3rd, 2025