Bulk activity and milestone move

 

Right click on a day in a lane and select Shift tags forward…

  • Enter the number of days you would like to shift tags forward
  • Activity tags and milestones advance according to the plan’s settings for weekends and holidays
  • Dependencies, including inter-lane ones, are preserved
  • If Apply shift to all lanes is selected, the entire plan shifts by a certain number of days (up to 20). Both undo and redo actions are supported